                              ATWOOD OCEANICS, INC.
             (Exact name of registrant as specified in its charter)

                         COMMISSION FILE NUMBER 1-13167

              TEXAS                                 74-1611874
 (State or other jurisdiction of       (I.R.S. Employer Identification No.)
 incorporation or organization)

    15835 Park Ten Place Drive                        77084
          Houston, Texas                            (Zip Code)
 (Address of principal executive offices)

        Registrant's telephone number, including area code: 281-749-7800
                                       N/A
         (Former name or former address, if changed since last report.)
================================================================================



ITEM 7. EXHIBITS

EXHIBIT 99.1        CONTRACT STATUS SUMMARY AT JULY 16, 2003



ITEM 9.    REGULATION FD DISCLOSURE

     ExxonMobil  Exploration  and Production  Malaysia Inc.  ("ExxonMobil")  has
exercised  an  option  to  extend  the  contract  for the  SEAHAWK  for one year
commencing December 18, 2003. For the one year extension,  the operating dayrate
will be fixed at $50,000.  ExxonMobil  has the right to  terminate  the contract
after the  completion of the first six months of the  extension  period with one
hundred twenty (120) days written notice.

     The ATWOOD  HUNTER has  completed its contract in Israel and is being moved
to  Egypt  where  it  will be  stacked  while  waiting  for  its  next  contract
opportunity.  The ATWOOD  SOUTHERN  CROSS is expected to complete it contract in
Italy prior to the end of July 2003, at which time it will be moved to Egypt for
stacking while waiting for its next contract opportunity. Contract opportunities
for both drilling units are being pursued in the Mediterranean  Area, as well as
in other areas of the world.

     The worldwide  offshore  demand for drilling units continues to be impacted
by political  uncertainties and soft market  conditions.  With the ATWOOD HUNTER
and ATWOOD  SOUTHERN  CROSS expected to incur  significant  idle time during the
fourth  quarter of fiscal 2003,  the Company  anticipates a net loss of $4 to $6
million for the quarter ended September 30, 2003. The current  near-term outlook
has not  weakened  the  Company's  optimism  about the  longer-term  outlook and
fundamentals of the offshore drilling market.

     Additional  information  with  respect  to the  Company's  Contract  Status
Summary  July  16,  2003 is  attached  hereto  as  Exhibit  99.1  which is being
furnished in accordance with Rule 101 (e)(1) under  Regulation FD and should not
be deemed to be filed.

     Statements  contained  in  this  report  with  respect  to the  future  are
forward-looking  statements.  These statements reflect  management's  reasonable
judgment with respect to future events. Forward-looking statements involve risks
and uncertainties. Actual results could differ materially from those anticipated
as a result of various  factors:  the  Company's  dependence  on the oil and gas
industry;  the  risks  involved  in  the  construction  of a  rig;  competition;
operating  risks;  risks involved in foreign  operations;  risks associated with
possible  disruption in operations  due to terrorism;  risks  associated  with a
possible  disruption in operations due to war; and governmental  regulations and
environmental  matters.  A list of  additional  risk factors can be found in the
Company's  annual  report on Form 10-K for the year ended  September  30,  2002,
filed with the Securities and Exchange Commission.









SIGNATURES

         Pursuant to the requirements of the Securities Exchange Act of 1934,
the registrant has duly caused this report to be signed on its behalf by the
undersigned hereunto duly authorized.


                                              ATWOOD OCEANICS, INC.
                                              (Registrant)



                                              /s/ James M. Holland
                                              James M. Holland
                                              Senior Vice President

                                              DATE:    July 16, 2003








                                  EXHIBIT INDEX


EXHIBIT NO.                        DESCRIPTION

99.1               Contract Status Summary at July 16, 2003








                                                            EXHIBIT 99.1
                                               ATWOOD OCEANICS, INC. AND SUBSIDIARIES
                                                      CONTRACT STATUS SUMMARY
                                                          AT July 16, 2003



 NAME OF RIG                LOCATION               CUSTOMER                          CONTRACT STATUS
 ===========                ========               ========                          ================
SEMISUBMERSIBLES -
==================

                                                               
ATWOOD FALCON              MOBILIZATION TO   MURPHY SABAH OIL CO. AND   The rig is being mobilized to Malaysia to
                           MALAYSIA          SARAWAK  SHELL             drill one well for Murphy Sabah Oil Co and
                                                                        one well for Sarawak Shell.  The drilling of
                                                                        these wells should commence around the third
                                                                        week of July, 2003 and should take between
                                                                        100 and 140 days to complete.  Murphy has an
                                                                        option to drill one additional well at a
                                                                        later date.  Following completion of its work
                                                                        in Malaysia, the rig will be moved to Japan
                                                                        to drill two wells estimated to take 100 to
                                                                        120 days to complete.

ATWOOD HUNTER              MOVING TO EGYPT                              The rig is being relocated to Egypt where it
                                                                        will be stacked while waiting for its next
                                                                        contract opportunity.  There are short-term
                                                                        contract opportunities for the rig commencing
                                                                        in early September 2003.  Longer-term
                                                                        contract opportunities for additional work
                                                                        are being pursued in the Mediterranean area,
                                                                        as well as areas outside of the Mediterranean.

ATWOOD EAGLE               ANGOLA            ESSO EXPLORATION ANGOLA    The rig is drilling the second well of a firm
                                             (BLOCK 15) LIMITED         three well contract with ESSO off the coast
                                             ("ESSO")                   of Angola.  ESSO has options for four
                                                                        additional wells.  If no option wells are
                                                                        drilled, the contract could terminate around
                                                                        early August 2003.  Contract opportunities
                                                                        for additional work in Angola and elsewhere
                                                                        in West Africa are being pursued.

SEAHAWK                    MALAYSIA          EXXONMOBIL EXPLORATION &   The rig's current contract terminates in
                                             PRODUCTION MALAYSIA        December 2004, with an option for the
                                             INC.  ("EMEPMI")           Operator to extend.  EMEPMI has the right to
                                                                        terminate the contract after the completion
                                                                        of the first six months of the extension
                                                                        period (which commences in December 2003)
                                                                        with 120 days written notice.

ATWOOD SOUTHERN CROSS      MEDITERRANEAN    EDISON GAS S.p.A.           The rig is contracted to EDISON to work on
                           SEA              ("EDISON")                  three plug and abandonment wells which is
                                                                        expected to be completed prior to the end of
                                                                        July 2003.  Contract opportunities for
                                                                        additional work are being pursued in the
                                                                        Mediterranean area, as well as areas outside
                                                                        of the Mediterranean.

SEASCOUT                   UNITED STATES                                The SEASCOUT was purchased in December 2000
                           GULF OF MEXICO                               for future conversion to a tender-assist
                                                                        unit, similar to the SEAHAWK, once an
                                                                        acceptable contract opportunity is secured.
                                                                        The rig is currently coldstacked.

CANTILEVER JACK-UPS -
=====================
VICKSBURG                  MALAYSIA         EXXONMOBIL EXPLORATION &    In October 2002, the rig commenced a two-year
                                            PRODUCTION MALAYSIA INC.    drilling program (with an option by EMEPMI
                                                                        for one additional year), with EMEPMI having
                                                                        the right to terminate the drilling program
                                                                        after one year with at least 120 days notice
                                                                        period.

ATWOOD BEACON              SINGAPORE                                    The final commissioning of the ATWOOD BEACON
                                                                        continues on schedule.  The shipyard portion
                                                                        of the construction was completed in May
                                                                        2003, with equipment commissioning and
                                                                        testing currently being carried out.
                                                                        Following completion of equipment
                                                                        commissioning and testing estimated to be around
                                                                        August 1, 2003, the rig will be moved to
                                                                        Malaysia to drill three wells plus options
                                                                        for five additional wells for Murphy Sarawak
                                                                        Oil Co., Ltd.   The three firm wells are
                                                                        expected to be completed in October 2003.
                                                                        Contract opportunities for
                                                                        additional work following completion of the
                                                                        Murphy contract are being pursued.

SUBMERSIBLE -
==============
RICHMOND                   UNITED STATES    SPINNAKER EXPLORATION       The rig is currently working under a
                           GULF OF MEXICO   COMPANY, L.L.C.             one-well, plus options for two additional
                                                                        wells contract for Spinnaker Exploration
                                                                        Company, L.L.C.  The one firm well is
                                                                        expected to be completed in early August 2003.

MODULAR PLATFORMS -
===================
GOODWYN 'A' /NORTH         AUSTRALIA        WOODSIDE ENERGY LTD.        There is currently an indefinite planned
RANKIN 'A'                                                              break in drilling activity for the two
                                                                        client-owned rigs managed by the Company.
                                                                        The Company is involved in maintenance of the
                                                                        two rigs for future drilling programs.